Advanced Project Management

104 views 6:45 am 0 Comments August 19, 2023

OPS 936
Advanced Project
Management
Dr Sander Kroes
[email protected]
Week 7 – Lecture
Acknowledgement for contributions to Slide Content:
Dr Marco Antonio Amaral Feris

For this Lecture
Feedback on WBS and Procurement
Feedback on Cost Management (and Cashflow)
• Time Management
3
WBS and Procurement
Feedback

4
Cost Management and
Cash Flow

5
Time Management
Consider your constraints
• What activities – As Soon As Possible (to manage
emerging risks)
• What activities – As Late As Possible (eg cashflow)
• Operational (e.g. council limitations)
• Interactions – with Principle (site access)
• Interactions – with other contractors (competition for
access, safety)
• Other organisational projects (priorities)
Developing a Gantt Chart
• Start WBS tasks, then for each task;
• Decide how (resources)
• Estimate Time
• Determine dependencies
• Plot task on timeline
Generally completed by software you heard about in OPS939

line Description Duration Start Finish Depend. People Resources
1.2.1 Survey 3 d 12/6/23 14/6/23 32 JSS P/L
1.2.2 Dig hole 2 d 15/6/23 16/6/23 33 Tom Excav.
1.2.3 Insert Reo 3 d 17/6/23 19/6/23 34 Reo Crew

Developing a Gantt Chart
• Start WBS tasks, then for each task;
• Decide how (resources)
• Estimate Time
• Determine dependencies
• Plot task on timeline
Generally completed by software you heard about in OPS939

line Description Resources 12 13 14 15 16 17 18 19 20 21
1.2.1 Survey Excav.
1.2.2 Dig hole
1.2.3 Insert Reo

9

WBS Task Duration Start Date Responsible % Complete
Off site Preparations 39 2/02/2021 Elect 74%
On site Preparations 15 13/03/2021 Elect 0%
Conduct Performance 6 28/03/2021 Elect 0%
Pack up and Clean up 11 3/04/2021 Elect 0%
Contract Obligations Achieved 0 14/04/2021 Elect 0%
Collect Marketing Material 10 14/04/2021 Elect 0%
Write Report 20 24/04/2021 Elect 0%

 

Days 20 40 60 80 100

Critical Path Work completed Milestone
Another Example
Consider Various Gantt Charts for PMP
• One for where the Contractor’s project(s) sits within the
Principal’s project
• One that shows the major deliverables/activities of your
project (scope of work)
• Note that for contractors, one of the major risk is usually
denied access.
Make sure you know how you are going to
manage this (eg contractual terms for handling variations).
• Principals should also consider how delays are managed
and avoided (where possible).

11

12