OPS 936
Advanced Project
Management
Dr Sander Kroes
[email protected]
Week 7 – Lecture
Acknowledgement for contributions to Slide Content:
Dr Marco Antonio Amaral Feris
For this Lecture
• Feedback on WBS and Procurement
• Feedback on Cost Management (and Cashflow)
• Time Management
3
WBS and Procurement
Feedback
4
Cost Management and
Cash Flow
5
Time Management
Consider your constraints
• What activities – As Soon As Possible (to manage
emerging risks)
• What activities – As Late As Possible (eg cashflow)
• Operational (e.g. council limitations)
• Interactions – with Principle (site access)
• Interactions – with other contractors (competition for
access, safety)
• Other organisational projects (priorities)
Developing a Gantt Chart
• Start WBS tasks, then for each task;
• Decide how (resources)
• Estimate Time
• Determine dependencies
• Plot task on timeline
Generally completed by software you heard about in OPS939
line | Description | Duration | Start | Finish | Depend. | People | Resources |
1.2.1 | Survey | 3 d | 12/6/23 | 14/6/23 | 32 | JSS P/L | |
1.2.2 | Dig hole | 2 d | 15/6/23 | 16/6/23 | 33 | Tom | Excav. |
1.2.3 | Insert Reo | 3 d | 17/6/23 | 19/6/23 | 34 | Reo Crew |
Developing a Gantt Chart
• Start WBS tasks, then for each task;
• Decide how (resources)
• Estimate Time
• Determine dependencies
• Plot task on timeline
Generally completed by software you heard about in OPS939
line | Description | Resources | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 |
1.2.1 | Survey | Excav. | ||||||||||
1.2.2 | Dig hole | |||||||||||
1.2.3 | Insert Reo |
9
WBS Task | Duration | Start Date | Responsible | % Complete |
Off site Preparations | 39 | 2/02/2021 | Elect | 74% |
On site Preparations | 15 | 13/03/2021 | Elect | 0% |
Conduct Performance | 6 | 28/03/2021 | Elect | 0% |
Pack up and Clean up | 11 | 3/04/2021 | Elect | 0% |
Contract Obligations Achieved | 0 | 14/04/2021 | Elect | 0% |
Collect Marketing Material | 10 | 14/04/2021 | Elect | 0% |
Write Report | 20 | 24/04/2021 | Elect | 0% |
Days 20 40 60 80 100 |
Critical Path Work completed Milestone
Another Example
Consider Various Gantt Charts for PMP
• One for where the Contractor’s project(s) sits within the
Principal’s project
• One that shows the major deliverables/activities of your
project (scope of work)
• Note that for contractors, one of the major risk is usually
denied access. Make sure you know how you are going to
manage this (eg contractual terms for handling variations).
• Principals should also consider how delays are managed
and avoided (where possible).