Project Priority Evaluation Form

145 views 10:26 am 0 Comments May 10, 2023

Table 1. Project Priority Evaluation Form.

Must objectives

Must meet if impacts

Proposal

1

Proposal

2

Proposal

3

Proposal

4

Be safe, legal and comply with university policies

Y = yes

N = no

Earn at least $500

Y = yes

N = no

Can be completed within 9 weeks

Y = yes

N = no

Opportunity to learn project management

Y = yes

N = no

Want objectives

Relative Importance 1 – 100

Single project impact definitions

Weighted Score

Weighted Score

Weighted Score

Weighted Score

Earning potential

90

0: 500–750

1: 750–1500

2: >$1500

3: >$2000

Fun

30

0 = Non

1 = Some fun

2 = Much fun

Increase awareness of the charity

30

0 = No potential

1 = Low potential

2 = High potential

Resume worthy

40

0 = No potential

1 = Low potential

2 = High potential

Be featured on

local TV news

40

0 = No potential

1 = Low potential

2 = High potential

Total weighted score

Priority

Table 2. Shoreline Stadium Project.

ID

Activity

Duration

Predecessor(s)

1

Baseball Stadium

2

Clear stadium site

70 days

3

Demolish building

30 days

2

4

Set up construction site

70 days

3

5

Drive support piling

120 days

4

6

Pour lower concrete bowl

120 days

5

7

Pour main concourse

120 days

6

8

Install playing field

90 days

6

9

Construct upper steel bowl

120 days

6

10

Install seats

140 days

9

11

Build luxury boxes

90 days

9

12

Install jumbotron

30 days

9

13

Stadium infrastructure

120 days

9

14

Construct steel canopy

75 days

10

15

Light installation

30 days

10

16

Build roof supports

90 days

4

17

Construct roof

180 days

16

18

Install roof tracks

90 days

14

19

Install roof

90 days

17,18

20

Inspection

20 days

8,11,13,15,19