Table 1. Project Priority Evaluation Form.
Must objectives |
Must meet if impacts |
Proposal 1 |
Proposal 2 |
Proposal 3 |
Proposal 4 |
||||||
Be safe, legal and comply with university policies |
Y = yes N = no |
||||||||||
Earn at least $500 |
Y = yes N = no |
||||||||||
Can be completed within 9 weeks |
Y = yes N = no |
||||||||||
Opportunity to learn project management |
Y = yes N = no |
||||||||||
Want objectives |
Relative Importance 1 – 100 |
Single project impact definitions |
Weighted Score |
Weighted Score |
Weighted Score |
Weighted Score |
|||||
Earning potential |
90 |
0: 500–750 1: 750–1500 2: >$1500 3: >$2000 |
|||||||||
Fun |
30 |
0 = Non 1 = Some fun 2 = Much fun |
|||||||||
Increase awareness of the charity |
30 |
0 = No potential 1 = Low potential 2 = High potential |
|||||||||
Resume worthy |
40 |
0 = No potential 1 = Low potential 2 = High potential |
|||||||||
Be featured on local TV news |
40 |
0 = No potential 1 = Low potential 2 = High potential |
|||||||||
Total weighted score |
|||||||||||
Priority |
Table 2. Shoreline Stadium Project.
ID |
Activity |
Duration |
Predecessor(s) |
1 |
Baseball Stadium |
||
2 |
Clear stadium site |
70 days |
– |
3 |
Demolish building |
30 days |
2 |
4 |
Set up construction site |
70 days |
3 |
5 |
Drive support piling |
120 days |
4 |
6 |
Pour lower concrete bowl |
120 days |
5 |
7 |
Pour main concourse |
120 days |
6 |
8 |
Install playing field |
90 days |
6 |
9 |
Construct upper steel bowl |
120 days |
6 |
10 |
Install seats |
140 days |
9 |
11 |
Build luxury boxes |
90 days |
9 |
12 |
Install jumbotron |
30 days |
9 |
13 |
Stadium infrastructure |
120 days |
9 |
14 |
Construct steel canopy |
75 days |
10 |
15 |
Light installation |
30 days |
10 |
16 |
Build roof supports |
90 days |
4 |
17 |
Construct roof |
180 days |
16 |
18 |
Install roof tracks |
90 days |
14 |
19 |
Install roof |
90 days |
17,18 |
20 |
Inspection |
20 days |
8,11,13,15,19 |